Santos Loses Appeal for Huge Northern Territory Gas Works

Santos Loses Appeal for Huge Northern Territory Gas Works
Protesters taking part in a national day of action against mining giant Santos, in Sydney, Australia on December 3, 2020. (AAP Image/Dean Lewins)
AAP
By AAP
12/2/2022
Updated:
12/2/2022

Gas giant Santos has lost its bid to restart drilling at a multimillion-dollar gas field off the Tiwi Islands, but the company is confident the project can stay on track.

The full Federal Court on Friday dismissed Santos’s appeal, upholding an earlier decision that the offshore gas regulator should not have approved drilling in the Barossa gas field, 265 kilometres northwest of Darwin.

Tiwi Islander and Munupi man Dennis Tipakalippa in June launched legal action against Santos, claiming he was not consulted over the company’s environmental plan.

Federal Court judge Mordecai Bromberg first ruled in Mr Tipakalippa’s favour in September, finding the regulator should not have approved the environmental plan.

He ordered the approval to be set aside and drilling to be stopped, but Santos appealed the decision last month.

Santos argued Justice Bromberg did not properly consider what constituted a “relevant person” who needed to be consulted.

The company’s barrister, Christopher Horan KC, said under the regulations a relevant person was someone whose “functions, interests or activities” could be affected by the drilling work.

Mr Horan argued the Tiwi Islands’ traditional owners had a connection to sea country that was genuine. However, it did not constitute the type of legal interest required.

But Federal Court justices Susan Kenny, Debra Mortimer and Michael Lee rejected that proposition, saying the Tiwi Islanders’ interests were “immediate and direct”.

“We consider it clear that Mr Tipakalippa and the Munupi clan had interests within the meaning of (the regulations) that required them to be consulted,” the judges said.

“Within this regulatory framework, ‘interests’ include cultural and spiritual interests of the kind described in the sea country material in the drilling environment plan and attachments.”

Mr Tipakalippa said the court’s latest decision would put companies on notice.

“We want the whole world to hear our voice,” he said in a statement on Friday.

“We want the whole world to see our power. We have fought to protect our sea country from the beginning to the end, and we will never stop fighting.”

The Federal Court rejected Santos’s claim it would be unworkable to identify and consult with every traditional owner who held an interest in the project.

“These clans are identified by name,” the judges said.

“In contemporary Australia, there are a myriad of ways of contacting groups of First Nations peoples.

“Granted, a consultation with First Nations groups may not be as simple (or quick) as sending an email with a package of information.”

In a statement, Santos said it would revise its environment plan for the Barossa project and apply for all remaining approvals following the court ruling.

“Santos does not anticipate any material cost or schedule impact, and the first gas from the Barossa gas project remains on track to be delivered in the first half of 2025,” it said.

The federal government is also considering the implications for Australia’s offshore environment and safety regulatory regime.

“It is the government’s expectation that industry makes genuine and robust efforts to consult First Nations peoples as part of the regulatory approvals process,” a spokesperson for Resources Minister Madeleine King said.

The Australian Petroleum Production and Exploration Association has called on the government to reform regulations around consultation requirements.

“There is now the risk of more delays and obstacles in the progression of important energy projects,” a spokesperson said.

“This is not an issue that affects one company.”

The $US3.6 billion ($A5.5 billion) offshore natural gas development was expected to create up to 600 jobs and pipe gas 280km to the Darwin LNG facility when production began in 2025.

The company has previously said the project, which was 43 percent complete and on schedule before the September court decision, is one of the world’s lowest-cost new LNG supply projects.