Melbourne’s Metro Tunnel Project Runs Out Of Contingency Funds

Melbourne’s Metro Tunnel Project Runs Out Of Contingency Funds
A general view underground of part of the Metro Tunnel metropolitan rail infrastructure project in Melbourne, Australia, on Nov. 6, 2020. (Asanka Ratnayake/Getty Images)
Alfred Bui
6/23/2022
Updated:
6/23/2022

Victorian taxpayers may have to bear additional costs for Melbourne’s Metro Tunnel as the project has mostly used up its risk contingency funds.

A Victorian Auditor-General’s Office report stated that the project was expected to overspend on tunnels and stations by $364 million (US$252 million).

It also found that the Victorian government had tried to offset the overspends by descoping some project components and internally reallocating the funds.

The project is about three years away from its completion date of 2025, but Rail Projects Victoria (RPV)–a government agency responsible for managing major rail projects in the state–has spent or allocated 98 percent of the tunnel’s $740 million risk contingency funds, citing “a sequence of unplanned costs and unexpected risk events.”

The audit noted that the lack of further contingency funds posed a considerable budget risk to the RPV, given the complex and risky works involved.

In addition, the audit said the RPV told the Victorian government in May that additional funding would be needed to deliver the full scope of the project and settle potential contingency costs in the two financial years after 2023. However, the agency had not requested the extra funds.

As cost overruns have emerged, the Victorian government has consented to a recommendation to review the project’s budget and determine the additional funding it might require.

Project’s Scoping Variations

A general view of the Metro Tunnel under construction in Melbourne, Australia, on June 28, 2021. (Asanka Ratnayake/Getty Images)
A general view of the Metro Tunnel under construction in Melbourne, Australia, on June 28, 2021. (Asanka Ratnayake/Getty Images)

Meanwhile, the audit found that thirty-three scoping variations occurred during the Metro Tunnel’s main construction phase, which cost the state $55.83 million.

One of the changes involved the slash of 27 kilometres of a high-capacity signalling system, or one-third of the initial coverage, to reallocate $91 million to other areas.

In another instance, the Victorian government approved the descoping of several “wider network enhancements” to free up $236 million for various overspent areas.

The estimated cost of the tunnel amounts to $12.36 billion, but it does not include $182 million in extra operational expenditures and another $41 million in COVID-19 claims.

Victorian Transport Infrastructure Minister Jacinta Allan said the state was impacted by COVID-related workforce issues and supply chain disruptions.

“This is a project that remains facing some challenges on cost,” she said.

“You can’t just set aside COVID. This is something we’re faced with (and) New South Wales reported on these matters just yesterday.”

Meanwhile, Opposition transport infrastructure spokesman Matt Bach allegedly said that the transport infrastructure minister deceived Victorian residents by shifting blame for the project’s overspends.

“Labor has shown time and time again that it can’t manage major projects, and it is sending our state broke,” he said.

Apart from financial issues, the audit said the tunnel project could cause damage to medical and scientific equipment near two of its stations due to electromagnetic interference caused by trains.

The Victorian Department of Transport and Rail Projects Victoria has agreed to carry out risk mitigation plans before train testing starts in June 2023.

The construction of the Metro Tunnel is expected to be finalised by 2025, one year earlier than scheduled.

Alfred Bui is an Australian reporter based in Melbourne and focuses on local and business news. He is a former small business owner and has two master’s degrees in business and business law. Contact him at [email protected].
Related Topics